FAQ

WHAT ARE THE REQUIREMENTS NEEDED FOR THE FOLLOWING PERMITS

I. SIGNAGE

A. Installation

  1. Letter request from Bldg. Admin or unit owner/contractor noted by Bldg. Admin
  2. Layout with dimensions
  3. Perspective

B. Cleaning/Repair/Removal of Signage

  1.  Letter request from Bldg. Admin or unit owner/contractor noted by Bldg. Admin
  2. Picture of signage

II. STREAMER

A. Installation

  1. Letter request from Bldg. Admin or unit owner/contractor noted by Bldg. Admin
  2. Layout with dimensions
  3. Perspective

III. EXTERIOR WORKS

A. Repainting/Waterproofing/Repair works

  1. Letter request from Bldg. Admin or contractor noted by Bldg. Admin
  2. Received info from the neighboring buildings (Note: Guaranty Deposit)

B. Cleaning

  1. Letter request from Bldg Admin or Contractor (noted by Bldg Admin)

IV. RENOVATION

A. Interior Renovation

  1. Letter request from Bldg Admin or unit owner/contractor (noted by Bldg Admin)
    Three (3) sets Architectural Drawing (Signed & Sealed by Arch. Or Civil Engineer &
  2. Signed by Owner)
  3. Copy of CCT or Contract of Lease

B. Façade Rehabilitation/Renovation

  1. Letter request from Bldg. Owner/Admin
  2. Elevation plan

C. Renovation with Expansion/Additional Floor Area

  1. Letter request from Bldg. Owner/Admin
    Five (5) sets Architectural Drawing (Signed & Sealed by Arch. Or Civil Engineer &
  2. Signed by Owner)
  3. Revised Parking Plans
    Certified true copy of Transfer Certificate of Title (TCT) with annotation of Amended
  4. Consolidated and Revised Deed Restrictions

V. NEW BUILDING CONSTRUCTION

  1. Letter request from the member/developer
    Nine (9) sets Architectural drawing duly signed and sealed by the Architect/Engineer
  2. and signed by the member/developer on all sheets
  3. One (1) set each: Plumbing & Sanitary; Fire Protection; Mechanical; & Electrical
    Certified true copy of Transfer Certificate of Title (TCT) with annotation of Amended
  4. Consolidated and Revised Deed Restrictions
  5. Two (2) sets Excavation plan showing system of soil protection
  6. Payment of processing fee and/or Construction Guaranty Deposit
  7. Payment of Development Charge
  8. Submission of Performance Bond

VI. Vehicle Passage/Stationing

A. Letter of request 

  1. Date of Time 
  2. Location
  3. Nearest Bldg.
  4. Palate No.
  5. Type of Vehicle
    -if Mobile Crane/Trailer
    Submit Drawing+ JHA.

VII. Telecom/Utility Installation (Telco cable/manhole, drainage/Water/Sewer/Power Connection)

A. AERIAL

  • Letter of Request 
  • Drawing
  • JHA
  • APMC R-O-W

B. EXCAVATION 

  1. Installation Of:
  2. Telecom Conduit & Cable
  3. Drainage /Power
    • Letter of Request
    • Drawing of Excavation
    • APMC R-O-W
    • MAPA Clearance (After Submission of VI. and VII.)
      • *if on side only, NO MAPA

4. Sewer/Water Connection

    • Letter of Request
    • Drawing of Excavation 
    • APMC R-O-W
    • MAPA Clearance
    • Drawing from MWCI
    • JHA 

5. Others

    • Letter of Request
    • Drawing
    • MAPA
    • APMC

VIII. Road Closure 

Tower Crane Installation/Del. H/V/A/C, Genset/Etc. Lifting

    • Letter of Request
    • Traffic Management Plan/Drawing
    • Advisory to affected Bldgs.
    • JHA
    • Drawing (positioning of equipment)
    • MAPA clearance (as Applica)

IX. Opening of Manhole 

A. Repair and Maintenance 

  • MWCI Sewer /Water /Drainage/power
  • Letter & Drawing 

B. Telco

  • Letter of Request (from telco) Drawing (w/manhole Loc.)
  • JHA

X. Drone Flying for Video /Photoshoot

  1. Letter of Request (indicate purpose, Bldg.  be covered, Date/Time
    Street to be covered model of drone.
  2. Endorsement from Bldg. Admin.
  3. Affidavit (Notarized) stating.
    • Will not take shoot towards other bldg. & Individuals
    • Will not Violate the privacy of anyone.

     4. Photocopy of CAAP license of drone operation
     5. CAAP permit for the activity.


XI. Repair and Maintenance Telco Facilities

A. Underground

  • Letter of Request (If contractor, submit Endorsement from telco)
  • Drawing Showing Location of all Manholes.
  • JHA
  • Traffic Management Plan (Drawing).

B. AERIAL

  • Letter of Request (If contractor, Submit Endorsement from Telco)
  • Drawing 
  • JHA

XII. Construction Related Installation Roadway

A. Safety Net 

  1. Letter 
  2. Drawing
  3. NO objection

B. Tower Crane Operation 

Letter W/Endorsement from Developer

  1. Drawing Showing 
    • Footprint of boom 
    • Reach of boom

     2. No Objection from affected Bldg.
     3. JHA
     4. Third-party certificate of cranes safety.

C. Wrap-around Net

Inverted Umbrella (Cath pan)

  • Letter of Request 
  • Drawing

D. Board-up/ Sidewalk Ensure:

  • Letter of Request 
  • Plan /Section

E. Man hoist (Temporary Elevator)

  • Letter of Request 
  • Plan. Elev.+Section.

F. Signboard 

  • 1.Letter 
  • 2. Drawing/Photo/Location of Insta 1 later.

G. OSP (Overhead Road Safety Net)

  • Letter of Request 
  • Drawing 
  • No Objection from affected Bldg. 
  • JHA
  • Commitment Letter that the sidewalk.