Skip to content
Applicable Requirements
- Letter request from the member or developer.
- Letter request from the building administrator.
- Letter request from the telecommunication carrier/MERALCO.
- Authorization, certification or contract with lot owner.
- Right-of-way permit from Ayala Property Management Corp. (APMC)
- Clearance from the Makati Parking Authority (MAPA).
- Permit from the National Water Resources Board.
- Drawing showing details of excavation and/or installation. 03 sets
- Drawing showing details of repair including its location. 03 sets
- Drawing showing the details of the signage/installation including its location. 03 sets
- Drawing showing route/location of the installation or activity. 03 sets
- Drawing from Meralco or telecom carrier showing the details of the project. 03 sets
- Drawing showing details of fence/temporary facility (materials, elevations, alignment/location) 03 sets
- Photocopy of payment or official receipt and drawing from the Manila Water Co. (MWC).
- Payment of restoration cost.
- Payment of deposit.
- Architectural drawing duly signed and sealed by the Architect/Engineer and signed by the member-developer on all sheets. 09 sets
- Certified True Copy of Transfer Certificate of Title (TCT) with annotation of amended Consolidated and Revised Deed Restriction.
- Certified True Copy of TCT or Condominium Certificate of Title (CCT) or Contract of Lease.
- Architectural drawing duly signed and sealed by the Architect/Engineer and signed by the member-developer on all sheets. 03 sets
- Excavation plan showing system of soil protection. 01 set
- Revised Parking Plan.
- Payment of Plans Processing Fee and/or Construction Guaranty Deposit.
- Payment of Development Charge.
- Submission of Performance Bond.